New limestone caps arrived. Landscapers started installing pavers.
 
Floor crew arrived today and put down test stain in two rooms. Looks good. We've given them the go ahead for the rest of the house.
 
Stopped by to check out progress on the garage doors. They are almost ready for caulk and paint - we've decided to do that ourselves.
 
Exterior outlets and lights were installed today.
 
Shelves will be painted white.
 
Basement paint is almost complete.
 
Painters headed to the basement today. Landscapers were also back to continue on the patio.
 
Landscapers arrived to start setting edge stones for patio. Rear basement door was also installed.
 
Rear deck was installed over the flat roof.
 
More plumbing fixtures installed today