Basement doors and garage doors get first coats of paint.
 
Front steps and curb poure
 
Concrete crew was back today doing more demo and prep. They are getting ready to start on the upper portion of the drive.
 
Lower portion of the driveway was poured today. We are doing a sandwashed finish that will give us the look of aged concrete. Plan is that all concrete work with be done by the end of the week.
 
We've decided to install a series of french drains to help collect and get water away from the house. These were designed with the idea we could install a pump in the future, if need, to move additional water away from the house.

 
Spent the afternoon installing HVAC registers. These are all original registers that we had sandblasted and powder coated. They turned out great! We still need to touch up screws.